City of Muskegon Addresses Lead Service Lines: A Comprehensive Overview
| KEY POINTS |
|
Dan VanderHeide, City of Muskegon's Director of Public Works, presented an update on lead service line replacements. Muskegon's water is safe and has never exceeded EPA-mandated lead levels, but the city is proactively replacing all lead service lines. Replacements are done via large construction projects in neighborhoods (currently Oakview and Sheldon Park) and by the city for issues like new homes, low water pressure, or broken lines. A demonstration board showed the components of a service line, from the water main to the meter. The city replaces the entire service line up to the meter, but not internal household plumbing.
These replacements are funded through a 20-year loan from the Drinking Water State Revolving Fund, with a portion historically forgiven as grants. The city is advocating for continued grant funding, as declining grant percentages will increase costs for citizens. Homeowners are notified by mail and door hangers before replacements begin and can find information on the project and lead reduction resources at [MKGCity.com/lslr] (lower cases). The website includes a map showing the status of service lines (green for replaced/no lead, red for lead, yellow for previously connected to lead). Yellow lines are replaced due to the possibility of lead contamination in downstream galvanized steel pipes.
Replacements require access to the home's basement or crawl space. Contractors typically access the water main from inside the house, minimizing yard disruption, although some digging is necessary. The city aims to complete replacements by 2037 (federal mandate) or 2040 (state mandate), but hopes to finish sooner, potentially by mid-decade. The city prioritizes areas with the highest density of lead service lines for neighborhood projects. City-led replacements are driven by other factors like breaks or low pressure. Homeowners are encouraged to contact a plumber for replacing internal plumbing. The city sent letters to residents indicating the likely material of their service line, and will send additional notifications before replacement projects begin.
PLG_SYSTEM_PWAPROGRESSIVEWEBAPP_INSTALLIOS1 PLG_SYSTEM_PWAPROGRESSIVEWEBAPP_INSTALLIOS2